Salem
Back Up Next

Business Agent for Salem County:  Ray MacDowell


Salem 2 Generating Station, 2008

Steam Generator Replacement Outage

An old steam generator being rigged out of containment LU 322 Brother Steve Hancock
LU 322 Brothers Ryan Citrino & Gerry Reed The SPMT is positioned to receive a steam generator.

 

Salem 2 Generating Station, 2007

The long awaited arrival of the new steam generators for PSEG's Salem Unit 2 is here. The Replacement Steam Generators, or RSGs as they're known, are being delivered to PSEG the week of April 30, 2007. They will be stored on site until the upcoming Salem 2 outage next Spring. During that interim they will be made ready for placement inside the containment building.

LU 322 Brothers Bill Ulbin and Bob Derderian are both working on the project and were present when two of the RSGs, each weighing about 380 tons, were being made fast to the barge that will bring them to Artificial Island in Hancocks Bridge, NJ in early May.


Brother Bill Ulbin and PSEG Engineer Tina Nolte make ready to
board  the ship and observe offloading of the RSGs.


Pictured above is one of the huge shipboard cranes used to lift the RSGs out of the ship's hold and onto the waiting barge.

The new Steam Generators were manufactured by AREVA NP in France and transported by Big Lift Shipping to the United States. The Fagioli Group is providing the SPMTs and handling transport of the RSGs from the ship to PSEG by barge and overland using a SPMT to move them to where they will be stored onsite until the Steam Generator outage begins next Spring.

There were of course many other people who were involved in getting the new steam generators this far along in the project. This photo is of those who were present when the last RSG rolled off the barge at the Hope Creek slip on the evening of May 3, 2007.


Salem 1 Generating Station, 2007

Salem just finished a refueling outage for PSEG's Salem Unit 1 in the Spring of 2007 and is making preparations for the
Unit 2 steam generator replacement outage next Spring. The photos below are of LU 322 Pipefitters and Welders
working The SHAW Group Inc. in one of the fab shops at the plant.

Click on thumbnail for full size image.   Click on thumbnail for full size image.   Click on thumbnail for full size image.


Hope Creek Generating Station 2005

Two new watertube package boilers from Victory Energy were installed to replace the three aging
boilers which were part of the original plant design for auxiliary and heating steam.

Hope Creek Boiler Replacement. Copyright 2005, UA Local 322, All rights reserved.

Hope Creek Boiler Replacement. Copyright 2005, UA Local 322, All rights reserved.  Hope Creek Boiler Replacement. Copyright 2005, UA Local 322, All rights reserved.  Hope Creek Boiler Replacement. Copyright 2005, UA Local 322, All rights reserved.

Hope Creek Boiler Replacement Crew. Copyright 2005, UA Local 322, All rights reserved.

 


Salem Generating Station, 2004

.

Pipefitters and Boilermakers who worked on the project pose for the camera.

LP bundle replacements on 22 E &W Moisture Separator Reheaters at Salem Generating Station in April, 2005. The Project was completed 48 hours ahead of schedule and under budget thanks to the hard work and dedication of both UA and BM Journeymen working the project. PCI was the contractor and all supervision are Members of LU 597 Chicago.

 

Hit Counter


Home ] Atlantic ] Burlington ] Camden ] Cape May ] Cumberland ] Gloucester ] Ocean ] [ Salem ] Submit Photos ]